SL. No Achievements
01  The capacity of the substation has changed from 11 MVA to 26.66 MVA.
02  Due to the construction of new distribution lines, the electricity demand increased from 3 MW to 7 MW.
03  Number of distribution transformers increased from 80 to 112.
04  Annual imports increased from 20 million units to 33 million.
05  Number of customers increased from 10000 to 18314.
06  3 villages of Barguna Sadar Upazila are newly electrified.
07  The electrified area of Barguna municipality increased from 80 percent to 100 percent.